Mongolia DMP 132kV Substation Project

Owner:United Energy Systems Limited Liability Company
Scope:132/6kV Darkhan Steel Expansion Substation Project
Introduction:The Mongolia DMP project is an EPC contract signed by the Power Construction Company in May 2014, and it is the first 110kV substation general contracting project executed by the Power Construction Company in Mongolia. The total contract duration is 90 days, with a start date of July 18, 2014, and it was completed on October 10, 2014, making it the fastest completed general contracting project by the Power Construction Company within the contractually agreed timeframe.